Abernethy Trust (Barry Edmondson)

Kilmalieu, Nr Ardgour

Emailbarry.edmondson@abernethy.org.uk
InstallerGilkes (no MCS approval as >50 kW system)
Capacity (kW)89
Grant£1,620,000.00
Installation Date06 October 2010
Report Date11 April 2010
kWH Generated94,000
Est Payback Time (Years)3
Installation Cost£350,000.00

ROCs/FiTs/RHI Info

Currently negotiating for FITs (17.8p/kWh).

Warranty

1 or 2 years depending on which parts. There is a 20 year agreement for the Trust to pay parts and Gilkes to provide labour. Gilkes are being paid 14.5 % of actual income in return for £75,000 reduction in bill (due to increase in turbine size from 50kW to 89 kW). This also covers the 20-year maintenance deal.

Planning Issues

No major planning or SEPA issues. SEPA approval given prior to current SEPA policy of 'presumed rejection' of all hydro schemes under 100 kW.

Technology Description

'Run-of-river' micro-hydro 10.5" 'Turgo' turbine

Owner Comments

Misc. grant info:
£100,000 from Community Energy Scotland
£25,000 from LEADER
£37,000 from Highlands and Islands Enterprise
Estimated annual generation: 344,000 kWh.